SAAQclic: Guilbault’s office pleads ignorance regarding cost overruns

SAAQclic: Guilbault’s office pleads ignorance regarding cost overruns

Current and former staff members of the office of Geneviève Guilbault, Minister of Transport and Sustainable Mobility, claimed that they only learned of cost overruns for SAAQclic last February with the report from the Auditor General of Quebec (VGQ).

However, documentation referring to an increase in the contract bill with the consortium was sent to the office in 2023, according to what was revealed during the Gallant Commission on Friday morning.

The then chief of staff, Geneviève Cantin, acknowledged that she had been made aware of the contractual strategy in the summer of 2023 for the SAAQ’s IT modernization project called CASA.

Related:

The document presents a $45.7 million “addendum” concluded in November 2022 and another one to come that would cause the bill to jump from the initial $458 million contract.

“I just want to be clear, these are not cost overruns. These are amendments. (…) When I look at this, I see it as the contractual strategy. The amendments are part of the contract,” she testified before the commission of inquiry.

This statement caused Commissioner Denis Gallant to react strongly.

“The lawyer in me says that an additional $45 million is a cost overrun, unless I’m mistaken,” he pointed out.

–This report by La Presse Canadienne was translated by CityNews